ROADMAP

Roadmap

Every piece of work between here and a finished platform, what each one waits on, and how long each one takes.

How to read it

Each phase is drawn as its own chart. An arrow runs from a piece of work to whatever cannot start until it is right, so the shape of each phase is what the work actually depends on rather than an order we chose.

Every box carries how long that piece of work takes, and every phase how long it runs. A phase is shorter than its boxes added together because work that can run alongside other work does. These are planning figures rather than commitments.

  • Complete
  • Under way
  • Waiting on an answer
  • To come

Phase 0

Orientation

3 to 4 weeks

14 of 18 complete

Stage 1Stage 2Stage 3Stage 4Stage 5Establish what is being built. Under 1 week.Establish what is beingbuiltUnder 1 weekBuild the development site. 1 week.Build the development site1 weekSettle how we write to clients. Under 1 week.Settle how we write toclientsUnder 1 weekSettle the Gallagher visual language. Under 1 week.Settle the Gallaghervisual languageUnder 1 weekStand up our own tenant and domain. Under 1 week.Stand up our own tenantand domainUnder 1 weekBuild the photography library. Under 1 week.Build the photographylibraryUnder 1 weekName planning documents consistently. Under 1 week.Name planning documentsconsistentlyUnder 1 weekApply the punctuation rule everywhere. Under 1 week.Apply the punctuation ruleeverywhereUnder 1 weekGallagher-ise the club comparison tool. 2 weeks.Gallagher-ise the clubcomparison tool2 weeksWrite the house rules. Under 1 week.Write the house rulesUnder 1 weekPublish the architecture page. Under 1 week.Publish the architecturepageUnder 1 weekTest AJG guest access. Under 1 week.Test AJG guest accessUnder 1 weekArchive older progress entries. Under 1 week.Archive older progressentriesUnder 1 weekRequire hardware keys to sign in. Under 1 week.Require hardware keys tosign inUnder 1 weekOrganise the project documentation. Under 1 week.Organise the projectdocumentationUnder 1 weekTake feature requests on the site. 1 week.Take feature requests onthe site1 weekDraw the roadmap as a chart. Under 1 week.Draw the roadmap as achartUnder 1 weekPublish the roadmap. Under 1 week.Publish the roadmapUnder 1 week

Phase 1

Foundations

1.5 to 2 months

11 of 21 complete

Stage 1Stage 2Stage 3Stage 4Stage 5Decide what the server may read. 1 week.Decide what the server mayread1 weekWrite the threat model. 1 week.Write the threat model1 weekDecide how a gap is shown. 1 week.Decide how a gap is shown1 weekAgree how the code is organised. Under 1 week.Agree how the code isorganisedUnder 1 weekWrite the engineering charter. 1 week.Write the engineeringcharter1 weekDesign the permanent vessel identifier. 2 weeks.Design the permanentvessel identifier2 weeksDesign how people sign in. 2 weeks.Design how people sign in2 weeksMatch historic spreadsheets to ships. 2 weeks.Match historicspreadsheets to ships2 weeksDesign how keys are held and withdrawn. 2 weeks.Design how keys are heldand withdrawn2 weeksSettle the custodian key mathematics. 2 weeks.Settle the custodian keymathematics2 weeksDesign who may do what. 1 week.Design who may do what1 weekDesign recovery when access is lost. 1 week.Design recovery whenaccess is lost1 weekDesign the encryption model. 2 weeks.Design the encryptionmodel2 weeksSecurity review for Gallagher IT. 1 week.Security review forGallagher IT1 weekSpecify how the custodians agree. 1.5 weeks.Specify how the custodiansagree1.5 weeksChoose the resharing. Under 1 week.Choose the resharingUnder 1 weekDesign the data model. 2 weeks.Design the data model2 weeksDesign the machine on AJG premises. 2 weeks.Design the machine on AJGpremises2 weeksDesign how firms are kept apart. 1 week.Design how firms are keptapart1 weekChoose the technology and hosting. 1 week.Choose the technology andhosting1 weekRedesign the index as a mergeable structure. 2 weeks.Redesign the index as amergeable structure2 weeks

Phase 2

Skeleton and proving ground

1.5 to 2 months

2 of 13 complete

Stage 1Stage 2Stage 3Stage 4Stage 5Build the browser test harness. Under 1 week.Build the browser testharnessUnder 1 weekSet up the codebase. 1 week.Set up the codebase1 weekHarden the checks after review. Under 1 week.Harden the checks afterreviewUnder 1 weekStand up the environments. 1 week.Stand up the environments1 weekEstablish how we test. Under 1 week.Establish how we testUnder 1 weekAutomated checks on every change. 1 week.Automated checks on everychange1 weekBring across the visual design. 1 week.Bring across the visualdesign1 weekBuild key management. 3 weeks.Build key management3 weeksBuild sign in and session checks. 2 weeks.Build sign in and sessionchecks2 weeksBuild the database and its access rules. 2 weeks.Build the database and itsaccess rules2 weeksBuild recovery when access is lost. 1 week.Build recovery when accessis lost1 weekWrite the architecture documentation. Under 1 week.Write the architecturedocumentationUnder 1 weekBuild the completeness check. 1 week.Build the completenesscheck1 week

Phase 3

The Broker Portal

1.5 to 2 months

1 of 16 complete

Stage 1Stage 2Stage 3Stage 4Club comparison on published market figures. 1 week.Club comparison onpublished market figures1 weekInvite people and set what they see. 1 week.Invite people and set whatthey see1 weekCreate and edit renewal records. 2 weeks.Create and edit renewalrecords2 weeksNever show a sample figure as real. Under 1 week.Never show a sample figureas realUnder 1 weekCollect specimen documents. Under 1 week.Collect specimen documentsUnder 1 weekHistory, undo and restore. 2 weeks.History, undo and restore2 weeksSpreadsheet import with preview and correction. 2 weeks.Spreadsheet import withpreview and correction2 weeksSearch and saved filters. 2 weeks.Search and saved filters2 weeksRead figures off certificates and invoices. 3 weeks.Read figures offcertificates and invoices3 weeksFlag records that do not add up. 1 week.Flag records that do notadd up1 weekFleet schedules: one renewal year and across years. 2 weeks.Fleet schedules: onerenewal year and acrossyears2 weeksRoll a fleet into the next year. 1 week.Roll a fleet into the nextyear1 weekBulk import, holding what does not add up. 2 weeks.Bulk import, holding whatdoes not add up2 weeksPremium estimate from comparable vessels. 1 week.Premium estimate fromcomparable vessels1 weekExport to spreadsheet and sendable fleet schedule. 1 week.Export to spreadsheet andsendable fleet schedule1 weekRepopulate the book from source spreadsheets. 2 weeks.Repopulate the book fromsource spreadsheets2 weeks

Phase 4

The vessel archive

1 to 1.5 months

0 of 8 complete

Stage 1Stage 2Stage 3Vessel records and search. 2 weeks.Vessel records and search2 weeksIdentity timeline, and asking when unsure. 2 weeks.Identity timeline, andasking when unsure2 weeksHold, attach and search documents. 2 weeks.Hold, attach and searchdocuments2 weeksOwner, operator and manager contacts. 1 week.Owner, operator andmanager contacts1 weekShip movement over time. 3 weeks.Ship movement over time3 weeksMove between a ship and its records. 1 week.Move between a ship andits records1 weekShow what is missing in a vessel's document history. 1 week.Show what is missing in avessel's document history1 weekFleets and ownership change. 2 weeks.Fleets and ownershipchange2 weeks