ROADMAP
Roadmap
Every piece of work between here and a finished platform, what each one waits on, and how long each one takes.
Current as at 9 September 2026. Updated when we post a progress entry.
How to read it
Each phase is drawn as its own chart. An arrow runs from a piece of work to whatever cannot start until it is right, so the shape of each phase is what the work actually depends on rather than an order we chose.
Every box carries how long that piece of work takes, and every phase how long it runs. A phase is shorter than its boxes added together because work that can run alongside other work does. These are planning figures rather than commitments.
Complete Under way Waiting on an answer To come
Consolidate the project orientation. Under 1 week. Consolidate the project orientation Under 1 week Build the development site at dev.ajgmanifest.com. 1 week. Build the development site at dev.ajgmanifest.com 1 week Formalise the public copy style. Under 1 week. Formalise the public copy style Under 1 week Formalise the Gallagher visual language. Under 1 week. Formalise the Gallagher visual language Under 1 week Stand up the suppliers own Microsoft 365 tenant and domain. Under 1 week. Stand up the suppliers own Microsoft 365 tenant and domain Under 1 week Build the photography library. Under 1 week. Build the photography library Under 1 week Name plan documents for their ledger rows. Under 1 week. Name plan documents for their ledger rows Under 1 week Remove every em and en dash from the repository. Under 1 week. Remove every em and en dash from the repository Under 1 week Write the standing brief and house rules. Under 1 week. Write the standing brief and house rules Under 1 week Write the published architecture page. Under 1 week. Write the published architecture page Under 1 week Test AJG guest access into the supplier tenant. Under 1 week. Test AJG guest access into the supplier tenant Under 1 week Archive older development log entries. Under 1 week. Archive older development log entries Under 1 week Harden the supplier tenant with hardware-key authentication. Under 1 week. Harden the supplier tenant with hardware-key authentication Under 1 week Establish the documentation structure. Under 1 week. Establish the documentation structure Under 1 week Build feature requests on the development site. 1 week. Build feature requests on the development site 1 week Draw the roadmap as a chart and show it every turn. Under 1 week. Draw the roadmap as a chart and show it every turn Under 1 week Publish the roadmap on the development site. Under 1 week. Publish the roadmap on the development site Under 1 week
Define the public/private data split. 1 week. Define the public/private data split 1 week Write the threat model. 1 week. Write the threat model 1 week Design the completeness doctrine. 1 week. Design the completeness doctrine 1 week Agree the repository structure. Under 1 week. Agree the repository structure Under 1 week Author the engineering charter. 1 week. Author the engineering charter 1 week Design the Manifest Vessel ID. 2 weeks. Design the Manifest Vessel ID 2 weeks Design admission and authentication. 2 weeks. Design admission and authentication 2 weeks Design historic spreadsheet resolution. 2 weeks. Design historic spreadsheet resolution 2 weeks Design key management: derivation custody grant rotation revocation. 2 weeks. Design key management: derivation custody grant rotation revocation 2 weeks Design authorisation. 1 week. Design authorisation 1 week Design break-glass and recovery. 1 week. Design break-glass and recovery 1 week Design the encryption model. 2 weeks. Design the encryption model 2 weeks Write the security architecture review for Gallagher. 1 week. Write the security architecture review for Gallagher 1 week Specify the custodians distributed key generation and proactive resharing. 2 weeks. Specify the custodians distributed key generation and proactive resharing 2 weeks Design the data model. 2 weeks. Design the data model 2 weeks Design the on-premises compute node. 2 weeks. Design the on-premises compute node 2 weeks Design tenancy and isolation. 1 week. Design tenancy and isolation 1 week Choose the stack and design the hosting. 1 week. Choose the stack and design the hosting 1 week
Phase 2
Skeleton and proving ground Build the browser harness. Under 1 week. Build the browser harness Under 1 week Scaffold the repository. 1 week. Scaffold the repository 1 week Harden the enforcement layer after the adversarial review. Under 1 week. Harden the enforcement layer after the adversarial review Under 1 week Stand up environments. 1 week. Stand up environments 1 week Establish the test pattern. Under 1 week. Establish the test pattern Under 1 week Automated checks on every change. 1 week. Automated checks on every change 1 week Port the visual system. 1 week. Port the visual system 1 week Build key management. 3 weeks. Build key management 3 weeks Build admission session and re-checking. 2 weeks. Build admission session and re-checking 2 weeks Build the schema row-level security and privileged functions. 2 weeks. Build the schema row-level security and privileged functions 2 weeks Build break-glass and recovery. 1 week. Build break-glass and recovery 1 week Write the architecture documentation. Under 1 week. Write the architecture documentation Under 1 week Build the completeness check. 1 week. Build the completeness check 1 week
Club comparison on published market figures. 1 week. Club comparison on published market figures 1 week Access control surface. 1 week. Access control surface 1 week Renewal records: create read edit. 2 weeks. Renewal records: create read edit 2 weeks Placeholder discipline. Under 1 week. Placeholder discipline Under 1 week Hold the specimen document corpus for ingestion design. Under 1 week. Hold the specimen document corpus for ingestion design Under 1 week History attribution undo and point-in-time restore. 2 weeks. History attribution undo and point-in-time restore 2 weeks Spreadsheet import with preview and correction. 2 weeks. Spreadsheet import with preview and correction 2 weeks Search and filters with saved filters. 2 weeks. Search and filters with saved filters 2 weeks Document ingestion from certificate and invoice PDFs. 3 weeks. Document ingestion from certificate and invoice PDFs 3 weeks Validation and the does-not-add-up queue. 1 week. Validation and the does-not-add-up queue 1 week Fleet schedules: one renewal year and across years. 2 weeks. Fleet schedules: one renewal year and across years 2 weeks Renewal year rollover. 1 week. Renewal year rollover 1 week Bulk spreadsheet import holding what does not reconcile. 2 weeks. Bulk spreadsheet import holding what does not reconcile 2 weeks Premium estimate from comparable vessels. 1 week. Premium estimate from comparable vessels 1 week Export to spreadsheet and sendable fleet schedule. 1 week. Export to spreadsheet and sendable fleet schedule 1 week Repopulate the book from source spreadsheets. 2 weeks. Repopulate the book from source spreadsheets 2 weeks
Phase 4
The vessel archive Vessel records and identifier search. 2 weeks. Vessel records and identifier search 2 weeks Identity timeline and referral where identity is uncertain. 2 weeks. Identity timeline and referral where identity is uncertain 2 weeks Document archive: hold attach and search. 2 weeks. Document archive: hold attach and search 2 weeks Owner operator and manager contacts. 1 week. Owner operator and manager contacts 1 week The movement plane. 3 weeks. The movement plane 3 weeks Navigate between a vessel and its renewal records both ways. 1 week. Navigate between a vessel and its renewal records both ways 1 week Show what is missing in a vessel's document history. 1 week. Show what is missing in a vessel's document history 1 week Fleets and ownership change. 2 weeks. Fleets and ownership change 2 weeks