Roadmap

Every piece of work between here and a finished platform, what each one waits on, and how long each one takes.

How to read it

Each phase is drawn as its own chart. An arrow runs from a piece of work to whatever cannot start until it is right, so the shape of each phase is what the work actually depends on rather than an order we chose.

Every box carries how long that piece of work takes, and every phase how long it runs. A phase is shorter than its boxes added together because work that can run alongside other work does. These are planning figures rather than commitments.

  • Complete
  • Under way
  • Waiting on an answer
  • To come

Phase 0

Orientation

3 to 4 weeks

13 of 17 complete

Consolidate the project orientation. Under 1 week.Consolidate the projectorientationUnder 1 weekBuild the development site at dev.ajgmanifest.com. 1 week.Build the development siteat dev.ajgmanifest.com1 weekFormalise the public copy style. Under 1 week.Formalise the public copystyleUnder 1 weekFormalise the Gallagher visual language. Under 1 week.Formalise the Gallaghervisual languageUnder 1 weekStand up the suppliers own Microsoft 365 tenant and domain. Under 1 week.Stand up the suppliers ownMicrosoft 365 tenant anddomainUnder 1 weekBuild the photography library. Under 1 week.Build the photographylibraryUnder 1 weekName plan documents for their ledger rows. Under 1 week.Name plan documents fortheir ledger rowsUnder 1 weekRemove every em and en dash from the repository. Under 1 week.Remove every em and endash from the repositoryUnder 1 weekWrite the standing brief and house rules. Under 1 week.Write the standing briefand house rulesUnder 1 weekWrite the published architecture page. Under 1 week.Write the publishedarchitecture pageUnder 1 weekTest AJG guest access into the supplier tenant. Under 1 week.Test AJG guest access intothe supplier tenantUnder 1 weekArchive older development log entries. Under 1 week.Archive older developmentlog entriesUnder 1 weekHarden the supplier tenant with hardware-key authentication. Under 1 week.Harden the supplier tenantwith hardware-keyauthenticationUnder 1 weekEstablish the documentation structure. Under 1 week.Establish thedocumentation structureUnder 1 weekBuild feature requests on the development site. 1 week.Build feature requests onthe development site1 weekDraw the roadmap as a chart and show it every turn. Under 1 week.Draw the roadmap as achart and show it everyturnUnder 1 weekPublish the roadmap on the development site. Under 1 week.Publish the roadmap on thedevelopment siteUnder 1 week

Phase 1

Foundations

1.5 to 2 months

8 of 18 complete

Define the public/private data split. 1 week.Define the public/privatedata split1 weekWrite the threat model. 1 week.Write the threat model1 weekDesign the completeness doctrine. 1 week.Design the completenessdoctrine1 weekAgree the repository structure. Under 1 week.Agree the repositorystructureUnder 1 weekAuthor the engineering charter. 1 week.Author the engineeringcharter1 weekDesign the Manifest Vessel ID. 2 weeks.Design the Manifest VesselID2 weeksDesign admission and authentication. 2 weeks.Design admission andauthentication2 weeksDesign historic spreadsheet resolution. 2 weeks.Design historicspreadsheet resolution2 weeksDesign key management: derivation custody grant rotation revocation. 2 weeks.Design key management:derivation custody grantrotation revocation2 weeksDesign authorisation. 1 week.Design authorisation1 weekDesign break-glass and recovery. 1 week.Design break-glass andrecovery1 weekDesign the encryption model. 2 weeks.Design the encryptionmodel2 weeksWrite the security architecture review for Gallagher. 1 week.Write the securityarchitecture review forGallagher1 weekSpecify the custodians distributed key generation and proactive resharing. 2 weeks.Specify the custodiansdistributed key generationand proactive resharing2 weeksDesign the data model. 2 weeks.Design the data model2 weeksDesign the on-premises compute node. 2 weeks.Design the on-premisescompute node2 weeksDesign tenancy and isolation. 1 week.Design tenancy andisolation1 weekChoose the stack and design the hosting. 1 week.Choose the stack anddesign the hosting1 week

Phase 2

Skeleton and proving ground

1.5 to 2 months

2 of 13 complete

Build the browser harness. Under 1 week.Build the browser harnessUnder 1 weekScaffold the repository. 1 week.Scaffold the repository1 weekHarden the enforcement layer after the adversarial review. Under 1 week.Harden the enforcementlayer after theadversarial reviewUnder 1 weekStand up environments. 1 week.Stand up environments1 weekEstablish the test pattern. Under 1 week.Establish the test patternUnder 1 weekAutomated checks on every change. 1 week.Automated checks on everychange1 weekPort the visual system. 1 week.Port the visual system1 weekBuild key management. 3 weeks.Build key management3 weeksBuild admission session and re-checking. 2 weeks.Build admission sessionand re-checking2 weeksBuild the schema row-level security and privileged functions. 2 weeks.Build the schema row-levelsecurity and privilegedfunctions2 weeksBuild break-glass and recovery. 1 week.Build break-glass andrecovery1 weekWrite the architecture documentation. Under 1 week.Write the architecturedocumentationUnder 1 weekBuild the completeness check. 1 week.Build the completenesscheck1 week

Phase 3

The Broker Portal

1.5 to 2 months

1 of 16 complete

Club comparison on published market figures. 1 week.Club comparison onpublished market figures1 weekAccess control surface. 1 week.Access control surface1 weekRenewal records: create read edit. 2 weeks.Renewal records: createread edit2 weeksPlaceholder discipline. Under 1 week.Placeholder disciplineUnder 1 weekHold the specimen document corpus for ingestion design. Under 1 week.Hold the specimen documentcorpus for ingestiondesignUnder 1 weekHistory attribution undo and point-in-time restore. 2 weeks.History attribution undoand point-in-time restore2 weeksSpreadsheet import with preview and correction. 2 weeks.Spreadsheet import withpreview and correction2 weeksSearch and filters with saved filters. 2 weeks.Search and filters withsaved filters2 weeksDocument ingestion from certificate and invoice PDFs. 3 weeks.Document ingestion fromcertificate and invoicePDFs3 weeksValidation and the does-not-add-up queue. 1 week.Validation and thedoes-not-add-up queue1 weekFleet schedules: one renewal year and across years. 2 weeks.Fleet schedules: onerenewal year and acrossyears2 weeksRenewal year rollover. 1 week.Renewal year rollover1 weekBulk spreadsheet import holding what does not reconcile. 2 weeks.Bulk spreadsheet importholding what does notreconcile2 weeksPremium estimate from comparable vessels. 1 week.Premium estimate fromcomparable vessels1 weekExport to spreadsheet and sendable fleet schedule. 1 week.Export to spreadsheet andsendable fleet schedule1 weekRepopulate the book from source spreadsheets. 2 weeks.Repopulate the book fromsource spreadsheets2 weeks

Phase 4

The vessel archive

1 to 1.5 months

0 of 8 complete

Vessel records and identifier search. 2 weeks.Vessel records andidentifier search2 weeksIdentity timeline and referral where identity is uncertain. 2 weeks.Identity timeline andreferral where identity isuncertain2 weeksDocument archive: hold attach and search. 2 weeks.Document archive: holdattach and search2 weeksOwner operator and manager contacts. 1 week.Owner operator and managercontacts1 weekThe movement plane. 3 weeks.The movement plane3 weeksNavigate between a vessel and its renewal records both ways. 1 week.Navigate between a vesseland its renewal recordsboth ways1 weekShow what is missing in a vessel's document history. 1 week.Show what is missing in avessel's document history1 weekFleets and ownership change. 2 weeks.Fleets and ownershipchange2 weeks

Back to the log